SEQ-1 Power sequencing: intermittent problems on power on or off

Severity Status Implementation
warning planned judgement, depends on NET-8

Looks at. Power states and ramps per rail, part requirements.

What it catches. A design where the order or timing in which rails come up and go down is not controlled, and some part on the board is sensitive to it: the umbrella entry for start-up and shutdown problems that SEQ-2, SEQ-7, SEQ-8 and SEQ-9 name one by one.

Why it matters. Rails ramp at different speeds depending on load, input voltage and temperature. A part powered before its IO rail, an IO bank driven before its supply, a reset released while a rail is still ramping: each works most of the time and fails one power-on in a hundred, the worst kind of field bug.

Example. A sensor on an always-on 3.3 V LDO and an MCU on a buck that starts 5 ms later: during those 5 ms the sensor's interrupt output (push-pull, high) drives the unpowered MCU pin and back-powers its rail through the ESD diode (BKF), so the MCU sometimes starts from a half-powered state and hangs.

How to check. Not a single rule: list the rails, their sources and enables, and the parts with sequencing requirements; better_erc can draw the start-up order from EN/PG chains (NET-8), the judgement whether it is enough stays with the reviewer.

Fix. Make the order explicit: EN from the previous rail's PG, a sequencer or PMIC, tracking (SS/TR) where the datasheet asks for it; scope the ramps at cold and hot.

References. SLVA470 §2 (sequential start-up with EN and PG), §3-4 (ratiometric and simultaneous); AM335x §6.1.