SEQ-4 Soft-start circuit with a MOSFET or resistor as load

Severity Status Implementation
warning planned hard, depends on NET-10, CFG-2

Looks at. Soft-start circuit, load capacitance and current.

What it catches. A discrete soft-start (a MOSFET with an RC on its gate, or an inrush resistor bypassed later), whose behaviour with the real load has not been worked out; with a known load, a report of the inrush current, ramp time and FET dissipation.

Why it matters. The ramp of a gate-RC soft start depends on the FET's Miller plateau and the load: a resistive load and a capacitive one give very different inrush currents and FET dissipation during the ramp. A soft start that is too slow cooks the FET in its linear region; one that is too fast does nothing. An inrush resistor that is never bypassed drops the rail under load.

Example. A PMOS (AO3401) with 100k gate-source and 1 µF gate capacitor switching 12 V into a board with 470 µF and 1 A of resistive load: the gate time constant is 100 ms, the FET spends tens of milliseconds in its linear region at several watts, beyond the SOA of a SOT-23 part.

How to check. Recognise the structure (FET with a capacitor on gate, resistor to source, NET-10), take load capacitance and current from the project (CFG-2), compute ramp time, peak current and energy in the FET, compare with its SOA.

Fix. Size the RC for the load, check the FET's safe operating area, or use a load switch or hot-swap controller with a specified slew rate.

References. SLVA716 §2.2 and §3.3 (adding a resistor to slow the rise time); SLVA670 §3.2 (discrete implementation), §4 (application examples: rise time from the inrush limit).